You are here: SE Asia New Straits Times M1's Service Disruption: We Had A Contingency Plan In Place

M1's Service Disruption: We Had A Contingency Plan In Place

  • PDF
straitstimes

Singapore: In its latest update on last week's major 3G disruption, M1 said Monday that its contingency plans had shortened the restoration of its network to days.

"In the absence of these contingency plans, the services would have taken about 12 to16 weeks to be fully restored," M1 said in a statement. Adding that it takes a "very serious view" of the service incident, M1 said its contingency plans involved increasing network capacity and signalling links between all the other mobile network switches.

M1's service disruption started when one of its vendors was upgrading transmission equipment at its network headquarters in International Business Park at 3am on Jan 15. This caused a power problem which set off gas suppression and water sprinkler systems. One of the telco's mobile network switches then tripped, causing service to be disrupted.

"Plan A" was then activated involving the re-linking its mobile network to an alternative network switch. While the links were being re-configured, Plan B was concurrently activated, it said.

-- Courtesy of The Straits Times